The African Renaissance Monument in Dakar
October 2022 – March 2023 · Assignment in Senegal

Dakar

An industrial assignment in Dakar: contributing to the OLEOSEN soap plant, from electrical installation through start-up testing.

The African Renaissance Monument at sunset in Dakar.
Oleosen · Industrial project

An international assignment on a major industrial project.

From October 2022 to March 2023, I contributed to the construction of OLEOSEN’s new soap plant in Dakar, working with site teams and specialist suppliers.

2,500 m²Factory footprint
> MAD 65mReported investment
> 30,000 t/yrReported capacity
2022–2023On-site assignment
01 / PROJECT CONTEXT

A new manufacturing facility in Dakar.

OLEOSEN, part of Lesieur Cristal within Groupe Avril, developed a soap manufacturing facility for the Senegalese and regional markets. The figures above describe the company-reported scale of the facility, not the results of my individual work.

02 / MY RESPONSIBILITIES

Coordinating installation and preparing systems.

During installation, I coordinated a team of 5 electricians, allocating tasks, tracking progress and liaising with other trades. My work included power and control circuits, instrument installation and calibration, and coordination with contractors.

Working with Ballestra and Mazzoni, I supported auxiliary systems such as pumps, steam valves and effluent handling, programmed supplementary automation equipment and collected PLC data for supervision.

03 / TESTING AND START-UP

Two months reserved for testing and adjustments.

Installation work was completed two months before the scheduled launch. The project teams used that period for start-up trials, functional checks and equipment adjustments before production began. This was a collective project achievement.

Explore the OLEOSEN project

Industrial figures and project context: Lesieur Cristal / OLEOSEN announcement (2022) ↗

A memory of Jamal in Dakar, Senegal
A memory from Dakar, Senegal
International project · OLEOSEN / Lesieur Cristal / Avril Group · October 2022 – March 2023

A new industrial soap factory in Dakar.

Involved in installation and commissioning of an industrial soap manufacturing facility, including electrical work coordination, instrumentation, automation integration and start-up tests.

65 M MAD+Reported investment
2 500 m²Facility footprint
30 000 t/an+Reported annual capacity
5Electricians coordinated

My technical contributions

  • Supervised five electricians, assigned daily tasks and tracked installation progress.
  • Installed and verified Siemens and Schneider Electric control and power circuits.
  • Installed, inspected and calibrated process instrumentation.
  • Technical coordination with Ballestra and Mazzoni, including auxiliary equipment: pumps, steam valves and effluent handling.
  • Programmed supplementary automation systems and collected PLC data for supervision and digitalization.
  • Participated in functional tests, troubleshooting and commissioning.

Outcome: work completed two months ahead of the planned launch date.

Facility figures published by Lesieur Cristal (2022); not claimed as individual achievements. Official OLEOSEN press release ↗